Learn about the ongoing Public Works and Facilities repair projects to county roads, right of ways and facilities from damage caused by Hurricane Ian.
Last Updated: 06/27/2024 Category: County Facilities Category: Sales Tax Funded Current Phase: Planning and Project Approval
Construct a new fire station at a location to be determinded, replacing the old fire station. New fire station will generally conform to a new prototype design for new and replacement stations. Includes land acquisition for station to be located nearby present location.William R Gaines Jr. Veterans Memorial Park Phase II
Last Updated: 06/27/2024 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Design Development
William R. Gaines Jr. Veterans Memorial Park phase II design and construction.Mid-County Library Hurricane Repairs
Last Updated: 06/27/2024 Category: County Facilities Current Phase: Design Development
Utilizing the Hurricane repair consultant contract as well as the construction manager at risk for Mid-County repairs contract, design and restore the Mid-County Library to its condition prior to the event. Utilize the opportunity to make improvements to the facility where applicable following the guidelines of the County's insurance policy.Last Updated: 06/27/2024 Category: County Facilities Category: Sales Tax Funded Current Phase: Planning and Project Approval
Construct a new Fire Station at a location to be determinded, replacing the old fire station. Includes land acquisition for station to be located nearby present location.Last Updated: 06/27/2024 Category: County Facilities Category: Sales Tax Funded Current Phase: Planning and Project Approval
Construct a new Fire Station at a location to be determinded.Last Updated: 06/27/2024 Category: Parks And Recreation Category: Sales Tax Funded Current Phase: Design Development
GC Herring Phase I design and construction. Redevelopment of the park will include necessary amenities for a community park as identified in the Parks and Recreation master Plan.Last Updated: 06/24/2024 Category: Parks And Recreation Current Phase: Planning and Project Approval
Creation of a master plan through the park design process and phase 1 development.Last Updated: 06/24/2024 Category: Parks And Recreation Current Phase: Planning and Project Approval
Park master plan for Lake Betty Park
Phase 1 of the Master Plan includes a toddler playspace, ropes/ninja style athletic course, picnic pavilions, walking paths, and an improved parking lot.
Peachland Boulevard at Harbor Boulevard Intersection Improvments
Last Updated: 06/24/2024 Category: Roadway Current Phase: Design Development
The design and construction of new turn lanes and traffic signal modifications at the intersection of Peachland Boulevard and Harbor Boulevard.